Administration > Application Administration > Service Level Management Administration > Recalculation > Running Recalculation Tasks
Running Recalculation Tasks
You generally run recalculation tasks after making retroactive changes.
To run a recalculation task:
- Select the Recalculation tab (Admin > Service Level Management > Recalculation).
- Locate the SLA which you want to recalculate, and click its Schedule button
to open the Recalculation Task dialog box.
- To define the start of the recalculation period, click the Recalculate from date and time to make changes in the calendar.
The recalculation period must begin before the Last Calculation date and time.
The earliest date at which the recalculation process can begin running is set in the Infrastructure Settings Manager. By default, the recalculation period is three months. It is not recommended to lengthen this period as the recalculation task takes longer for a longer period. For example, Service Level Management takes longer to recalculate a month than to recalculate a week. For details, see Editing Settings with the Infrastructure Settings Manager and Infrastructure Settings in Platform Administration.
- To define when the recalculation must begin: click the Schedule the task to start date and time to make changes in the calendar.
Note: If you have just created an SLA whose start date has the current date and time, and you choose to start the SLA now, Service Level Management immediately begins calculating the first hour. However, since the first hour's raw data has not yet been sent to the database, the results are of no value. In this case, choose to start the SLA in a few hours.
- Click OK.